Tennessee permit review deadlines

How long does it take to get a building permit in Tennessee?

Tennessee's deadlines sit on either side of the building permit. Since October 2024, an applicant can hire a registered third-party plans examiner, and the local government has 10 business days to respond.

Starting January 1, 2027, site plans and other development applications get their own clock: 30 business days for a first response, 60 for a decision, and automatic approval if the local government misses.

See the deadlines ↓

Current Tennessee state-level guidelines

10business days to respond when a third-party examiner has reviewed the plans
30business days for a first response on a site plan, from 2027
60business days to approve a development application or put it on an agenda, from 2027
2written deficiency reports is the limit on a development application, from 2027

The short answer

We found no statewide deadline in Tennessee for a local government's own building plan review. Two related rules do carry deadlines. First, an applicant can hire a third-party plans examiner registered with the state fire marshal. The local government then has 10 business days to approve the application, report deficiencies, or ask for more information, or it must refund the application fees. Second, Public Chapter 1044 takes effect January 1, 2027. It gives local governments 30 business days to respond to site plans, plats, and similar development applications and 60 business days to decide. A missed deadline means the submission is deemed approved. That law does not cover building permits.

By project type

Tennessee review deadlines.

Tennessee's two clocks cover different stages of a project.

Project typeDeadlineWhat to know
Building plans reviewed by a third-party examiner10 business daysFor the local government to approve, list deficiencies, or request information.
Site plans, plats, and development plans: first response30 business daysWritten deficiency report or request for information. Starts January 1, 2027.
Site plans, plats, and development plans: decision60 business daysApprove, or place on the next planning commission or governing body agenda.
Development application resubmittal30 business daysAfter the applicant documents that the deficiencies are fixed.

Public Chapter 1044 does not cover building, fire, mechanical, plumbing, or electrical permits, or rezonings and annexations.

When the clock runs out

What happens when a Tennessee local government misses the deadline.

Third-party review: fees refunded.

If the local government does not respond in 10 business days, it must refund the application fees. The applicant can then refile with the state fire marshal's office, which has 10 business days.

Development applications: deemed approved.

From 2027, a submission is deemed approved if the local government misses the deadline.

Development applications: two deficiency reports.

After a second report, staff must deny with written reasons and refund 50% of the fees, approve with conditions, or send the application to the next agenda.

Faster permit approvals start with more efficient plan review.

See how your team can spend less time chasing comments, waiting on other disciplines, and tracking down the status of a review, without changing your permitting system or CDP.

See how it works

Recent changes

What changed, and when.

October 1, 2024

Third-party plan review and inspection takes effect

An applicant who uses a third-party examiner for plans must also use one for the inspections that follow.

January 1, 2027

Public Chapter 1044 takes effect

Adds T.C.A. 7-51-2204, the development review deadlines.

Common questions

Tennessee building permit deadlines, answered.

How long does it take to get a building permit in Tennessee?

We found no statewide deadline for a local government's own building plan review. If you use a registered third-party plans examiner, the local government has 10 business days to respond.

Does Tennessee's new 2027 law cover building permits?

No. Public Chapter 1044 covers site plans, plats, road and drainage plans, and similar development applications. Building permits fall under a different part of state law.

What happens if a Tennessee city ignores a third-party plan review?

It must refund the application fees. The applicant can withdraw the review and refile with the state fire marshal's office.

How do Tennessee building departments keep up with these deadlines?

Three habits show up in the departments that hit the clock. They check applications for missing items in the first few days. They let building, fire, planning, and engineering review the same plans at the same time. And they track the days left on every review, so a manager can step in before a deadline passes.

See how collaborative review works in e-PlanREVIEW.

Read it for yourself

Sources.

Keep exploring

Deadlines in other states.

If you review plans in Tennessee

Working under Tennessee's review clock? See how e-PlanSoft can help you hit it consistently.

Meeting a review deadline starts with a good intake process, disciplines that work together, and a clear view of every review in progress.

Book a demoSee how collaborative review works →

This page summarizes public laws, rules, and city review practices in Tennessee as of November 12, 2026. Deadlines vary by location and permit type. These summaries are for reference, not legal advice. Check the linked sources and local requirements for the rules that apply to your project.