Utah permit review deadlines

How long does it take to get a building permit in Utah?

Utah gives a city or county 14 business days to finish plan review on a house, duplex, or townhome, and 21 business days on larger residential buildings.

If the local government misses the deadline and misses again after the applicant asks, it cannot enforce plan review on plans stamped by a licensed architect or structural engineer.

See the deadlines ↓

Current Utah state-level guidelines

14business days to review plans for a one- or two-family home or townhome
21business days for other residential buildings
3business days to screen a new application
3business days to provide an inspection before a third-party firm can step in

The short answer

Utah law gives a city or county 14 business days to complete plan review for a one- or two-family dwelling or townhome, and 21 business days for other residential structures built under the International Building Code. The clock runs after a three-business-day screening period. If the local government misses the deadline, the applicant can request that it finish, and it then has 14 or 21 days. If it misses again and a licensed architect or structural engineer has stamped the plans, the local government may not enforce the plan review requirement. The rules are in Utah Code 10-20-909 for cities and 17-79-810 for counties.

By project type

Utah permit review deadlines.

Utah's deadlines apply to residential construction in cities and counties.

Project typeDeadlineWhat to know
Screening period3 business daysAfter the applicant submits. The review clock starts when it ends.
One- or two-family home or townhome14 business daysTo complete plan review.
Other residential structures under the International Building Code21 business daysLodging establishments are not included.
After the applicant requests completion14 or 21 daysA second deadline once the first is missed.
Building inspection3 business daysIf the local government cannot inspect in time, the applicant can hire a listed third-party firm.

Step by step

How Utah's review clock works.

Three business days of screening.

The local government checks that the application has what the law lists: contact information, site plan, construction drawings, energy code documents, structural calculations, and a compliance statement.

Fourteen or 21 business days of plan review.

Plan review covers all the reviews a city requires to issue the building permit.

The applicant can demand completion.

After a miss, the local government gets one more 14 or 21 days.

Stamped plans move ahead.

After a second miss, the local government may not enforce plan review on plans stamped by a licensed architect or structural engineer.

What this means for a review team

  • Plan review means every review needed for the permit, so all disciplines share the 14 business days.
  • The completeness list is in the statute. Intake can check against it on day one.
  • Inspections have their own 3-business-day clock, and the local government pays the third-party firm.

When the clock runs out

What happens when a Utah department misses the deadline.

Stamped plans skip plan review.

If the local government misses the deadline twice, it may not enforce a plan review requirement on plans stamped by a licensed architect or structural engineer.

Third-party inspections at the regulator's cost.

If an inspection cannot be provided within 3 business days, the applicant can hire a firm from the local list, and the local regulator pays for the inspection.

Certificate of occupancy in one business day.

After the final inspection report from a third-party firm, the regulator must issue the certificate of occupancy no later than one business day.

Faster permit approvals start with more efficient plan review.

See how your team can spend less time chasing comments, waiting on other disciplines, and tracking down the status of a review, without changing your permitting system or CDP.

See how it works

Recent changes

What changed, and when.

May 1, 2024

SB 185 takes effect

Adds third-party inspections when a local government cannot inspect in 3 business days.

2025

The law moves in the Utah Code

The municipal section is renumbered to 10-20-909 and the county section to 17-79-810. The current text, effective November 6, 2025, includes the three-business-day screening period.

City by city

How Utah cities handle review times.

Salt Lake City works under the state clock and posts matching targets.

State deadline

Salt Lake City

Salt Lake City has 14 business days to review plans for houses and townhomes and 21 for apartment buildings under state law. The city posts matching targets, plus a 30-day goal for commercial projects.

Read the source →

City details come from each city's public pages as of November 12, 2026. Cities change their targets and processes often, so check the linked source for the current version.

Common questions

Utah building permit deadlines, answered.

How long does it take to get a building permit in Utah?

For a house, duplex, or townhome, the city or county has 14 business days to complete plan review after a three-business-day screening period. Larger residential buildings get 21 business days. We found no state deadline for commercial projects.

What happens if a Utah city misses the plan review deadline?

The applicant can ask the city to finish, which starts a second 14 or 21 days. If the city misses again and the plans are stamped by a licensed architect or structural engineer, it may not enforce the plan review requirement.

What counts as a complete application in Utah?

State law lists it: contact information for the applicant and contractor, a scaled site plan, construction plans and drawings, energy code documentation, structural calculations, and a compliance statement. A geotechnical report can be required on steep lots.

Can I hire my own inspector in Utah?

Only if the city or county cannot provide the inspection within 3 business days of the request. Then you can hire a firm from the local third-party list, and the local regulator pays for it.

How do Utah building departments keep up with these deadlines?

Three habits show up in the departments that hit the clock. They check applications for missing items in the first few days. They let building, fire, planning, and engineering review the same plans at the same time. And they track the days left on every review, so a manager can step in before a deadline passes.

See how collaborative review works in e-PlanREVIEW.

Read it for yourself

Sources.

Keep exploring

Deadlines in other states.

If you review plans in Utah

Working under Utah's review clock? See how e-PlanSoft can help you hit it consistently.

Meeting a review deadline starts with a good intake process, disciplines that work together, and a clear view of every review in progress.

Book a demoSee how collaborative review works →

This page summarizes public laws, rules, and city review practices in Utah as of November 12, 2026. Deadlines vary by location and permit type. These summaries are for reference, not legal advice. Check the linked sources and local requirements for the rules that apply to your project.