Georgia permit review deadlines

How long does it take to get a building permit in Georgia?

Georgia has two permit clocks. Building plan review has a 30-day limit, and an applicant can hire a private reviewer at any time. A 2026 law, SB 447, added a separate 45-day clock for land-disturbance permits.

The two are easy to mix up. SB 447 is often called the Georgia permit shot clock, but its deadlines and fee refunds apply to the land-disturbance permit, which comes before the building permit on most new projects.

See the deadlines ↓

Current Georgia state-level guidelines

5business days to say whether a building permit application is complete
30days for the local government to review building plans
45days to issue or deny a land-disturbance permit
50%off the local fees when a private provider does the plan review

The short answer

For building permits, Georgia law gives a local building official 5 business days to say whether an application is complete, and 30 days in total to review the plans. The applicant can hire a private professional provider, a licensed engineer or architect, to do the plan review instead, and the local fees drop by 50%. For land-disturbance permits, a 2026 law called SB 447 sets a separate clock: 5 days to check completeness, 45 days to issue or deny the permit, 20 days for the first resubmittal, and 14 days for later ones. If a local government misses that clock, it must refund the application fees, and the applicant can ask a superior court to step in.

By project type

Georgia permit review deadlines.

Georgia's deadlines depend on which permit you are asking for. The first three rows cover building permits. The last four cover land-disturbance permits under SB 447.

Project typeDeadlineWhat to know
Building permit: completeness check5 business daysThis time counts toward the 30 days. The clock pauses if the application is sent back as incomplete.
Building permit: plan review30 daysWhen it accepts the application, the local government must say whether it can meet 30 days. The applicant can use a private provider either way.
Building permit: revised plansRest of the 30 days, plus 5 business daysLater rounds of revisions get 5 business days each.
Land-disturbance permit: completeness check5 daysIf the applicant hears nothing, the application counts as complete.
Land-disturbance permit: first decision45 daysThe permit must be issued or denied within 45 days of filing.
Land-disturbance permit: first resubmittal20 daysNew comments must relate to the earlier comments or to what the applicant changed.
Land-disturbance permit: later resubmittals14 daysThe same limit on new comments applies.

The land-disturbance clock pauses while a state agency reviews part of the application. Some of its rules do not apply to developments of regional impact, and the law has a narrow local exception. Check the statute for your project.

Step by step

How Georgia's review clock works.

Land disturbance usually comes first.

On most new construction, the site needs a land-disturbance permit before building starts. Since July 1, 2026, the local government has 5 days to check that application and 45 days to issue or deny it.

The building permit has its own clock.

The building official has 5 business days to say whether the application is complete, and 30 days in total to review the plans.

The applicant can bring a private reviewer.

A licensed engineer or architect can review the plans instead. The building official then has 30 days from getting the application and the reviewer's affidavit to issue the permit or list what is wrong in writing. If the official does neither, the application is treated as approved.

Revisions move faster.

After the first set of corrections, the official has what is left of the 30 days plus 5 business days. After that, each round gets 5 business days.

When the clock runs out

What happens when a Georgia local government misses the deadline.

Land-disturbance fees are refunded.

If the local government does not issue or deny a land-disturbance permit in time, it must refund all the fees it collected with the application.

A court can order a decision.

The applicant can petition superior court, and the law gives that case priority on the court's calendar.

A privately reviewed building permit can be approved by default.

If the building official does not act within 30 days on plans reviewed by a private provider, the application is treated as approved.

Private inspection reports stand unless challenged quickly.

Under the 2026 law, the local government has two business days to flag problems in a private provider's inspection report in writing. After that, the inspection is treated as approved, according to a Nelson Mullins summary of the law.

Faster permit approvals start with more efficient plan review.

See how your team can spend less time chasing comments, waiting on other disciplines, and tracking down the status of a review, without changing your permitting system or CDP.

See how it works

Recent changes

What changed, and when.

2019

HB 493, the Private Permitting Review and Inspection Act

Set the 30-day plan review limit and let applicants hire a private professional provider for plan review and inspections.

July 1, 2026

SB 447 takes effect (Act 513)

Adds the land-disturbance clock, the fee refund, the court remedy, and the two-business-day rule for private inspection reports.

January 1, 2028

Public permit tracking is due

Local governments that issued more than 250 building permits in the year before must show permit status online, free and without a login.

City by city

How Georgia cities are applying the rules.

Cities are still adjusting to the 2026 law. Here is what two of them have published.

SB 447 notice

Augusta

Augusta's planning department says all new development applications get a 5-business-day completeness review as of July 1, 2026. It now takes new site, development, and grading applications on Mondays and Wednesdays only.

Read the source →
City target

Atlanta

Atlanta works under the state rules. The city's Office of Buildings also aims for roughly 10 business days on an initial review, which is an informal target with no penalty attached.

Read the source →

City details come from each city's public pages as of November 12, 2026. Cities change their targets and processes often, so check the linked source for the current version.

Common questions

Georgia building permit deadlines, answered.

How long does it take to get a building permit in Georgia?

State law gives the local government 30 days to review building plans, including 5 business days to check that the application is complete. Revised plans get the rest of that time plus 5 business days.

On new construction, add the land-disturbance permit that comes first. Since July 2026 that permit has its own 45-day limit.

What is the Georgia permit shot clock?

It is the name people use for SB 447, a 2026 law. It gives local governments 45 days to issue or deny a land-disturbance permit, then 20 days and 14 days on resubmittals, with a fee refund if they run late. It took effect on July 1, 2026.

Does SB 447 apply to building permits?

Its review deadlines and fee refund are written for land-disturbance permits. For building permits, SB 447 changed two other things. Private inspection reports now stand unless the local government objects within two business days, and larger local governments must post permit status online by January 1, 2028.

What happens if a Georgia local government misses the deadline?

On a land-disturbance permit, it must refund the application fees, and the applicant can ask a superior court to order a decision. On a building permit reviewed by a private provider, the application is treated as approved if the building official does not act within 30 days.

Can I hire a private reviewer in Georgia?

Yes. An applicant can hire a private professional provider for building plan review and inspections, whether or not the local government says it can meet its deadlines. The provider must be a licensed engineer or architect, or a qualified inspector for inspections, with no financial tie to the project. The local fees are cut by 50%.

How do Georgia building departments keep up with these deadlines?

Three habits show up in the departments that hit the clock. They check applications for missing items in the first few days. They let building, fire, planning, and engineering review the same plans at the same time. And they track the days left on every review, so a manager can step in before a deadline passes.

See how collaborative review works in e-PlanREVIEW.

Read it for yourself

Sources.

Keep exploring

Deadlines in other states.

If you review plans in Georgia

Working under Georgia's review clock? See how e-PlanSoft can help you hit it consistently.

Meeting a review deadline starts with a good intake process, disciplines that work together, and a clear view of every review in progress.

Book a demoSee how collaborative review works →

This page summarizes public laws, rules, and city review practices in Georgia as of November 12, 2026. Deadlines vary by location and permit type. These summaries are for reference, not legal advice. Check the linked sources and local requirements for the rules that apply to your project.