Massachusetts permit review deadlines

How long does it take to get a building permit in Massachusetts?

Massachusetts puts its deadline in the state building code. A building official must issue or deny a permit, in writing, within 30 days of filing.

A late permit is not approved automatically. The applicant's remedy is a complaint or an appeal to the state Building Code Appeals Board.

See the deadlines ↓

Current Massachusetts state-level guidelines

30days to issue or deny a building permit, counted from filing
0automatic approvals or fee refunds when the deadline is missed

The short answer

Under 780 CMR 105.3.1, a Massachusetts building official must examine a permit application and issue or deny the permit in writing within 30 days of filing. A denial must state the reasons. If the official does not act in 30 days, the applicant can file a complaint with the official's appointing authority or the Building Official Certification Committee, or appeal to the Building Code Appeals Board for lack of action. The permit is not deemed approved.

By project type

Massachusetts permit review deadlines.

Massachusetts sets one statewide deadline in the building code.

Project typeDeadlineWhat to know
Any building permit30 daysTo issue or deny in writing. Counted from the filing date.

Step by step

How Massachusetts's review clock works.

The clock starts at filing.

The code does not set a separate completeness period.

The official issues or denies within 30 days.

The decision must be in writing.

A denial states its reasons.

The official must say in writing why the application was rejected.

When the clock runs out

What happens when a Massachusetts official misses the 30 days.

A complaint against the official.

Failure to act in 30 days can lead to a complaint with the appointing authority or the Building Official Certification Committee.

An appeal for lack of action.

The applicant can take the case to the state Building Code Appeals Board.

Faster permit approvals start with more efficient plan review.

See how your team can spend less time chasing comments, waiting on other disciplines, and tracking down the status of a review, without changing your permitting system or CDP.

See how it works

City by city

How Massachusetts cities handle review times.

Boston adds a faster promise for one kind of project.

City target

Boston

Boston promises a seven-day turnaround for office renovation permits that come in with complete paperwork and an engineer's sign-off. The promise does not cover homes or retail, and there is no penalty if the city misses it.

Read the source →

City details come from each city's public pages as of November 12, 2026. Cities change their targets and processes often, so check the linked source for the current version.

Common questions

Massachusetts building permit deadlines, answered.

How long does it take to get a building permit in Massachusetts?

The state building code gives the building official 30 days from filing to issue or deny the permit. Many simple permits are faster.

Is a permit approved if the 30 days pass?

No. Massachusetts does not treat a late permit as approved. The applicant can file a complaint or appeal to the Building Code Appeals Board.

Where is the 30-day rule written?

In the Massachusetts State Building Code, 780 CMR, section 105.3.1. The section was last amended effective October 11, 2024.

How do Massachusetts building departments keep up with these deadlines?

Three habits show up in the departments that hit the clock. They check applications for missing items in the first few days. They let building, fire, planning, and engineering review the same plans at the same time. And they track the days left on every review, so a manager can step in before a deadline passes.

See how collaborative review works in e-PlanREVIEW.

Read it for yourself

Sources.

Keep exploring

Deadlines in other states.

If you review plans in Massachusetts

Working under Massachusetts's review clock? See how e-PlanSoft can help you hit it consistently.

Meeting a review deadline starts with a good intake process, disciplines that work together, and a clear view of every review in progress.

Book a demoSee how collaborative review works →

This page summarizes public laws, rules, and city review practices in Massachusetts as of November 12, 2026. Deadlines vary by location and permit type. These summaries are for reference, not legal advice. Check the linked sources and local requirements for the rules that apply to your project.