Pennsylvania permit review deadlines

How long does it take to get a building permit in Pennsylvania?

Pennsylvania's Uniform Construction Code sets clear clocks. A home permit must be granted or denied in 15 business days, or 5 when a licensed design professional certifies the plans.

If the official does not act, the home permit is deemed approved. Commercial permits get 30 business days, with no stated consequence for a miss.

See the deadlines ↓

Current Pennsylvania state-level guidelines

15business days to grant or deny a residential permit
5business days when a design professional certifies the plans
30business days to grant or deny a commercial permit

The short answer

Under 34 Pa. Code 403.63, a building code official must grant or deny a residential permit application within 15 business days of filing. If a Pennsylvania-licensed design professional prepared the drawings and certifies that they meet the code, the deadline is 5 business days. If the official does not act in time, the application is deemed approved. Commercial permits fall under section 403.43, which gives the official 30 business days and does not say what happens if the deadline is missed.

By project type

Pennsylvania permit review deadlines.

Pennsylvania's deadlines come from the Uniform Construction Code regulations.

Project typeDeadlineWhat to know
Residential permit15 business daysTo grant or deny, in whole or in part, from the filing date.
Residential permit with certified plans5 business daysPlans prepared and certified by a Pennsylvania-licensed design professional.
Commercial permit30 business daysNo deemed approval in the rule. A different deadline can be set for historic districts.

For both kinds of permit, the official and the applicant can agree in writing to extend the deadline by a set number of days.

Step by step

How Pennsylvania's review clock works.

The clock starts on the filing date.

There is no separate completeness period in the rule.

Residential: 15 or 5 business days.

The shorter deadline rewards plans certified by a licensed design professional.

Commercial: 30 business days.

The official may approve foundations or other parts early, and may allow deferred submittals with prior approval.

A denial is specific and in writing.

It must name the parts of the application that do not comply and cite the code provisions.

What this means for a review team

  • A residential deadline that ends in deemed approval leaves no slack for a queue.
  • Certified plans cut the window to 5 business days, so intake needs to spot them on day one.
  • Written extensions are the only way to add time.

When the clock runs out

What happens when a Pennsylvania department misses the deadline.

Residential permits are deemed approved.

If the official does not grant or deny within the deadline, the application is approved by rule.

Commercial permits have no stated consequence.

The commercial rule sets the 30 business days and stops there.

Faster permit approvals start with more efficient plan review.

See how your team can spend less time chasing comments, waiting on other disciplines, and tracking down the status of a review, without changing your permitting system or CDP.

See how it works

City by city

How Pennsylvania cities handle review times.

Pennsylvania's two largest cities work under the state code and add their own published numbers.

State deadline

Philadelphia

Philadelphia works under the state's 30-business-day commercial and 15-business-day residential deadlines. The city also tells applicants that a preliminary plan review takes up to 20 business days.

Read the source →
Executive order

Pittsburgh

Pittsburgh posts business-day review targets: 30 days for commercial and 15 for residential, with faster handling for emergencies. A 2026 permitting overhaul ordered by the mayor added one-day permits for simple jobs and a plan for a public dashboard.

Read the source →

City details come from each city's public pages as of November 12, 2026. Cities change their targets and processes often, so check the linked source for the current version.

Common questions

Pennsylvania building permit deadlines, answered.

How long does it take to get a building permit in Pennsylvania?

A residential permit must be decided in 15 business days, or 5 with plans certified by a licensed design professional. A commercial permit must be decided in 30 business days.

What does deemed approved mean in Pennsylvania?

If the building code official does not grant or deny a residential permit application within the deadline, the application is treated as approved.

Is a late commercial permit deemed approved in Pennsylvania?

No. The commercial rule sets a 30-business-day deadline but does not include a deemed approval.

How long is a Pennsylvania permit good for?

A residential permit becomes invalid if work does not begin within 180 days of issuance. It can be valid for no more than 5 years.

How do Pennsylvania building departments keep up with these deadlines?

Three habits show up in the departments that hit the clock. They check applications for missing items in the first few days. They let building, fire, planning, and engineering review the same plans at the same time. And they track the days left on every review, so a manager can step in before a deadline passes.

See how collaborative review works in e-PlanREVIEW.

Read it for yourself

Sources.

Keep exploring

Deadlines in other states.

If you review plans in Pennsylvania

Working under Pennsylvania's review clock? See how e-PlanSoft can help you hit it consistently.

Meeting a review deadline starts with a good intake process, disciplines that work together, and a clear view of every review in progress.

Book a demoSee how collaborative review works →

This page summarizes public laws, rules, and city review practices in Pennsylvania as of November 12, 2026. Deadlines vary by location and permit type. These summaries are for reference, not legal advice. Check the linked sources and local requirements for the rules that apply to your project.