Indiana permit review deadlines

How long does it take to get a building permit in Indiana?

Indiana has the shortest clock on the map. For homes, a local government has 3 business days to say whether an application is complete and 7 business days to finish plan review.

If it cannot meet those times, the applicant can move the work to a private provider and get most of the fee back. The rules took effect on January 1, 2026.

See the deadlines ↓

Current Indiana state-level guidelines

3business days to say whether a home permit application is complete
7business days to finish plan review once the application is complete
3business days to perform an inspection after a written request
$100is the most a local government keeps when work moves to a private provider

The short answer

For Class 2 structures, which are single-family homes, duplexes, and townhomes, Indiana gives a local government 3 business days to decide whether a building permit application is complete and 7 business days after that to finish plan review. Inspections are due within 3 business days of a written request. If the local government says it cannot meet those times, or misses them, the applicant can use a qualified private provider and the local government must refund its fees, less a convenience fee of up to $100. The rules are in Indiana Code 36-7-2.5 and took effect January 1, 2026.

By project type

Indiana permit review deadlines.

Indiana's deadlines apply to Class 2 structures: single-family homes, duplexes, and townhomes.

Project typeDeadlineWhat to know
Completeness check3 business daysThe local government must name any deficiencies. The clock restarts when revised materials come in.
Plan review7 business daysCounted from the notice that the application is complete.
Inspection3 business daysAfter a written request.
Permit after a private provider's plan review reportNext business dayThe local government issues the permit without a second review.

Step by step

How Indiana's review clock works.

Three business days to check the application.

The local government notifies the applicant in writing that the application is complete or says what is missing.

The local government says whether it can meet the clock.

After the application is complete, it must tell the applicant whether it can finish plan review in 7 business days and inspections in 3.

Seven business days for plan review.

If the local government said yes and then misses, it must issue the permit, or a limited permit for the compliant work, by the next business day.

A private provider is always an option.

The applicant can choose a licensed architect, engineer, or certified building official from the start, or switch if the local government cannot keep up.

What this means for a review team

  • The local government has to commit in writing. Saying yes to the 7 days and then missing it means issuing the permit the next business day.
  • Three business days at intake leaves no room for a queue.
  • Private providers are in the workflow from day one, so their reports need a clean way in.

When the clock runs out

What happens when a Indiana department misses the deadline.

The work can move to a private provider.

Qualified providers are licensed architects, engineers, and certified building officials who meet the law's independence rules.

Fees are refunded.

The local government refunds the fees for the work it no longer does. It may keep a convenience fee of up to $100.

The permit issues the next business day.

A local government that committed to the timeline and missed it must issue the permit or a limited permit.

Safety authority stays.

The local government keeps its stop-work authority for real public safety threats.

Faster permit approvals start with more efficient plan review.

See how your team can spend less time chasing comments, waiting on other disciplines, and tracking down the status of a review, without changing your permitting system or CDP.

See how it works

Recent changes

What changed, and when.

May 1, 2025

HEA 1005 is signed (Public Law 146-2025)

January 1, 2026

The permit and inspection deadlines take effect

Adds Indiana Code 36-7-2.5, Class 2 structure building permits.

Common questions

Indiana building permit deadlines, answered.

How long does it take to get a building permit in Indiana?

For a home, the local government has 3 business days to check the application and 7 business days to review the plans. These deadlines do not cover commercial projects.

What is a Class 2 structure in Indiana?

It is the state's term for one- and two-family homes and townhomes. The 2026 deadlines apply only to Class 2 structures.

What happens if an Indiana city misses the 7 business days?

If it told the applicant it could meet the deadline, it must issue the permit or a limited permit by the next business day. The applicant can also move the work to a private provider and get the fees refunded, less up to $100.

Can I use a private provider in Indiana?

Yes. An applicant can choose a private provider at the start or switch if the local government cannot meet the deadlines. The local government must issue the permit the next business day after it gets a complete plan review report.

How do Indiana building departments keep up with these deadlines?

Three habits show up in the departments that hit the clock. They check applications for missing items in the first few days. They let building, fire, planning, and engineering review the same plans at the same time. And they track the days left on every review, so a manager can step in before a deadline passes.

See how collaborative review works in e-PlanREVIEW.

Read it for yourself

Sources.

Keep exploring

Deadlines in other states.

If you review plans in Indiana

Working under Indiana's review clock? See how e-PlanSoft can help you hit it consistently.

Meeting a review deadline starts with a good intake process, disciplines that work together, and a clear view of every review in progress.

Book a demoSee how collaborative review works →

This page summarizes public laws, rules, and city review practices in Indiana as of November 12, 2026. Deadlines vary by location and permit type. These summaries are for reference, not legal advice. Check the linked sources and local requirements for the rules that apply to your project.